The construction of the 1-million-square-foot pad was completed 10 days ahead of schedule, despite 12 days of rain delay. The 110-acre Dollar General facility will create 538 new full-time jobs in San Antonio, Texas, and improve its distribution system for the southern United States.
How HCSS Software assisted with this project
HeavyBid makes Yantis Company more accurate and more consistent. It helps minimizes mistakes and helps ensure a concise and complete bid.
Project Description:
In September 2014, Yantis Company was awarded a $12.3 million mass grading and utilities contract for a new Dollar General Distribution Facility. Located just south of IH-10 on Foster Road, the site spanned over 100 acres.
The project was designed by Lockwood, Andrews & Newnam (LAN). Yantis worked directly for Dollar General on this project. Yantis’ contract included: 370,000 cubic yards of excavation; more than 496,000 cubic yards of embankment; 275,000 cubic yards of cement-treated pad; and 210,000 square yards of 12-inch cement-treated subgrade.
Yantis is currently installing more than 30,000 linear feet of storm drain, sewer, and water pipe as well as the dry electric package. The construction of the 1-million-square-foot pad began September 2, 2014, and was completed December 5, 2014, 10 days ahead of schedule with 12 days of rain delay.